Practical completion was fixed for 30 June. In November the employer is still deducting delay damages, the contractor insists the drawings arrived months late and the façade has begun to leak at the joints. Two claims have now fused into one dispute and the contract, read closely, answers neither cleanly. This is the moment a Construction Dispute Arbitrator is usually called in, and the questions he asks first are rarely the ones the parties expect.

Why delay and defect claims travel together

Delay and defects are often treated as separate grievances, but on a real project they feed each other. A contractor racing to recover lost time may compress inspection and testing, and defects follow. An employer who takes over a section that is not quite finished may then dispute whether later problems are incomplete work or latent defects. A tribunal has to untangle the two before it can price either.

The delay claim: proving cause, not just lateness

Lateness alone proves very little. The contractor must show that a risk event for which the employer bears responsibility actually delayed completion, and the employer must show that the contractor failed to finish on time and by how much.

The first hurdle is usually procedural. Under the FIDIC 2017 forms, a party must give a notice of claim as soon as practicable and no later than 28 days after it became aware or should have become aware, of the event giving rise to the claim. Failure to do so can defeat the entitlement altogether, although the Engineer must now confirm a time bar by giving notice within 14 days. In Obrascon Huarte Lain v Attorney General for Gibraltar, the English courts treated the 28-day notice as a condition precedent, and held that time ran from awareness of the event, not from the moment the delay itself became apparent.

Where the notice is valid, the tribunal turns to evidence. Competing programmes are tested through recognized delay analysis methods, such as as-planned versus as-built comparisons, time impact analysis or windows analysis and the Society of Construction Law Delay and Disruption Protocol is the usual reference point on concurrent delay. A credible programme expert, contemporaneous records and a clear chronology matter far more than the size of the number claimed.

Liquidated damages: certainty and its limits

Most contracts fix a daily rate for delay. English law, following Cavendish Square Holding v Makdessi, will enforce such a clause unless it is out of all proportion to the innocent party’s legitimate interest. In India, courts apply section 74 of the Indian Contract Act, which allows reasonable compensation up to the stipulated sum, and the Supreme Court in Kailash Nath Associates v DDA confirmed that loss generally has to be shown unless it is impossible to assess.

The employer’s own conduct can undo the whole structure. If its late instructions or variations contributed to the overrun, and the contract offers no workable mechanism to extend time, the employer may be unable to claim liquidated damages at all. This is the prevention principle at work, and it is one reason delay disputes so often turn on drafting.

The defect claim: notification, cause and cost

Defect disputes begin with the contractual timeline. Most standard forms provide a defects notification period after taking over, during which the contractor must remedy defects the employer notifies. Beyond it, the employer’s remedies depend on limitation periods and on whether the defect was latent.

The harder questions are technical. Was the failure caused by poor workmanship, non-compliant materials, a design fault, or inadequate maintenance? Responsibility follows the answer. A tribunal will also ask what the proper measure of loss is: the cost of reinstatement if that is reasonable, or the diminution in value where rebuilding would be out of proportion to the benefit. Independent expert evidence, preferably gathered before anything is repaired or altered, usually decides the outcome.

Why the choice of arbitrator matters

Delay and defect disputes reward a decision-maker who can read a programme as comfortably as a contract. That is why parties should think carefully about who sits as a Member of an arbitral tribunal and whether the dispute justifies one arbitrator or three.

Procedure matters too. The Arbitration Act 2025 gives English-seated tribunals an express power to dispose of issues summarily, which can shorten a dispute where liability on a single delay event can be decided without a full hearing. Where an English-law contract is being performed abroad, an English Arbitrator in USA can bridge the two systems without either side feeling out of its depth.

The subject matter is rarely confined to buildings. The same delay and defect questions arise on power plants and LNG terminals, where an Energy Dispute Arbitrator must follow the technical detail of EPC contracts, and in construction ventures where a Joint venture dispute arbitrator must also resolve how losses are shared between the partners. The International Arbitrator has acted as counsel in a multi-billion-dollar ICC construction arbitration and understands how these claims are built, tested and defended from both sides of the table.

Before you file

Three habits improve almost every delay or defect claim. Serve notices on time and in the form the contract requires. Preserve programmes, site records and physical evidence from the start. And separate the delay narrative from the defect narrative, so each can be proved on its own terms.

If your project is already in dispute, The International Arbitrator can help you assess whether arbitration is the right forum and how to structure the appointment.

Leave a Comment

Comments

No comments yet. Why don’t you start the discussion?

Leave a Reply

Your email address will not be published. Required fields are marked *